Renewable Power Cuts Have Already Cost Ceará R$ 800 Million

Federal government promises to compensate Ceará’s plants with about R$ 350 million, provided companies drop lawsuits.

Por O Fio

This is a translation of the original article in Portuguese. Read the original (Português).

Forced curtailment of power generation at renewable plants has already caused losses of R$ 800 million to Ceará, according to the newspaper Diário do Nordeste, a Brazilian newspaper. The phenomenon, known as curtailment, occurs when plants’ output is restricted even though energy is available to be delivered.

Between January 2025 and September 2026, about 25.3% of generation at Ceará’s plants was restricted. That is the third-highest rate in the country.

To try to offset the losses, the Ministry of Mines and Energy will compensate the affected companies, on one condition: they must drop lawsuits over the issue. Ceará’s plants are expected to receive about R$ 350 million, in the form of discounts on sector debts. According to the CCEE (the Electric Energy Trading Chamber), 158 plants in the state are eligible.

The compensation covers only part of the estimated losses. The R$ 350 million amounts to less than half of the R$ 800 million lost in the state.

The effects of the cuts also show up in investment. Across the country, 923 solar projects were returned in 2026, representing R$ 134 billion that will no longer be invested in the sector. In solar energy, Ceará returned 81 projects this year, according to Absolar (the Brazilian Solar Energy Association). Returning projects puts on hold the investment and jobs that clean energy expansion was expected to generate.

The same movement is hitting wind power. Aneel (Brazil’s National Electric Energy Agency) recorded 11 revocations of authorizations to build wind farms in 2025 and another 12 in 2026, through early November. In Ceará, new wind authorizations fell from 36 in 2022 to six in 2025.

The scenario contrasts with the image of green power the state has cultivated. Ceará is among the country’s major producers of solar and wind energy, but part of that output never reaches the system, in a situation where generation has grown faster than transmission lines.

On the grid, the state’s Secretariat of Economic Development reported that transmission line projects in the state total R$ 3.6 billion.

For consumers, the issue is the bill. Losses of this size in clean energy can end up passed on to the electricity system and, ultimately, to everyone’s tariff.

Reporting from Diário do Nordeste (p. 6, caderno Ceará: prejuízo com cortes de geração renovável), Diário do Nordeste (p. 7, caderno Nacional: cortes freiam o crescimento da energia renovável), Diário do Nordeste (p. 8, caderno Ceará: ressarcimento às usinas cearenses), Diário do Nordeste (p. 13, caderno Ceará: revogações de autorizações de parques eólicos).

Esta matéria reúne informações publicadas pelos veículos citados acima, com edição da redação do O Fio. Conheça nossa política editorial. Encontrou um erro? Fale com a redação.

Deixe um comentário

O seu endereço de e-mail não será publicado. Campos obrigatórios são marcados com *

Os comentários passam por moderação antes de aparecer. Seu e-mail não é publicado. Ofensas, ataques pessoais e propaganda são removidos. Veja a política de privacidade.