Data center requests total 38 GW, but Brazil’s grid has accepted only 7 GW

The volume is nearly three Itaipu dams’ worth of power; substations without room and lines taking up to seven years are holding up the queue.

Por O Fio

This is a translation of the original article in Portuguese. Read the original (Português).

Requests to connect data centers to Brazil’s electricity grid reach 38 gigawatts (GW), a volume equal to nearly three Itaipu hydroelectric plants. Only about 7 GW has been accepted so far by ONS, the National Electric System Operator, according to the Brazilian newspaper Folha de S.Paulo.

The bottleneck lies in the structure of the grid. Substations, which connect transmission lines to large consumers, can no longer handle additional load. To expand capacity, a new line would have to be built, a project that can take up to seven years to complete.

The bottleneck, therefore, is not only in power generation but in the path that electricity travels to reach the consumer. A data center may have land and money, but without an available connection point it cannot operate.

The problem is not exclusive to Brazil. In the United States, connecting a data center to the grid takes, on average, more than four years, according to Folha. The difference is that there, the wait is an average queue time, while in Brazil the first obstacle is the lack of capacity at substations, which leads to the rejection of a large share of requests.

Power is only one of the queues. An AI data center only begins operating when land, permits, buildings, chips and memory are all ready at the same time, and each item follows its own timeline. In practice, the longest queue determines when the project starts working. In both countries, in many cases, that queue is the one for power.

The stakes are high. In the United States, OpenAI plans a data center in Ohio with an investment of US$105 billion, an example of the scale of projects competing for grid capacity.

For Brazil, which hopes to attract this kind of investment, the bottleneck has a direct effect. Projects that cannot secure a connection may be delayed or move to other countries. The competition for a limited amount of power could also put pressure on costs across the electricity sector as a whole, not only on technology companies.

Of the 38 GW requested, therefore, about 31 GW remain without an approved connection point. Expanding the grid, with new substations and lines, is what will determine how much of this demand can be met and how long it will take.

Reporting from Folha de S.Paulo (p. 27, caderno nacional: Brasil tem 38 GW em pedidos de ligação de data centers), Folha de S.Paulo (p. 26, caderno nacional: Data centers de IA enfrentam filas por energia, chips e obras), Folha de S.Paulo (p. 26, Estados Unidos: Data centers enfrentam fila de espera por energia nos EUA).

Esta matéria reúne informações publicadas pelos veículos citados acima, com edição da redação do O Fio. Conheça nossa política editorial. Encontrou um erro? Fale com a redação.

Deixe um comentário

O seu endereço de e-mail não será publicado. Campos obrigatórios são marcados com *

Os comentários passam por moderação antes de aparecer. Seu e-mail não é publicado. Ofensas, ataques pessoais e propaganda são removidos. Veja a política de privacidade.