Connecting a data center to the power grid in the United States takes, on average, more than four years, according to data cited by the Brazilian newspaper Folha de S.Paulo. The timeline shows the scale of the bottleneck at a time when artificial intelligence companies are announcing ever-larger projects.
The transformer alone, a key piece of equipment for the connection, can take two to four years to arrive. A delay in any other required item, such as land, permits, power, buildings or chips, holds up the entire project.
That same week, Folha reported that OpenAI is planning a US$105 billion data center, roughly R$601.5 billion, in Ohio. According to the newspaper, Nvidia has backed and taken part in investments of this kind.
The contrast is stark: there is money for construction worth hundreds of billions of reais, but the power needed to run these facilities depends on equipment and connections that take years. Whoever reaches the grid first gains an advantage, and whoever waits sees the investment stall.
The profitability of the business helps explain the rush. According to Folha, Anthropic recorded a gross margin of 85.5% on the sale of generic tokens, the unit used to measure the use of AI models, between January and September 2026. The margin tripled in one year. Even so, the company remained in the red until its initial public offering (IPO), because of the costs of reserving computing capacity.
The problem is not only American. Brazil faces a similar queue, with requests for data center connections totaling 38 GW. The comparison shows that the competition for energy is global and that the pressure on prices and investment is likely to reach Brazil’s power system as well, with possible effects on electricity bills.
The responsible agencies have yet to detail how Brazilian requests will be prioritized and how the costs of expanding the grid will be divided.
Reporting from Folha de S.Paulo (p. 26, Estados Unidos: Data centers nos EUA levam mais de quatro anos para se conectar à rede), Folha de S.Paulo (p. 26, Estados Unidos: OpenAI planeja data center de US$ 105 bilhões em Ohio), Folha de S.Paulo (p. 27, Estados Unidos: Anthropic tem margem bruta de 85,5% com tokens genéricos).